Introduction Blurb

This page explains the process for installing a floor-based system. The steps below outline the order of preparing and leveling the skeleton, and supporting the system on the floor.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Next Steps & Delivery
Certification
Terms & Definitions


Anchor
Skill-Requirements
Skill-Requirements
Types of Installation:
(Off-the-Floor, Floor-Based, Virtuoso, Wall Bed, Paxton, Martha Stewart)

Installer Level Required:
(Jr. Apprentice Installer, Apprentice Installer, Journeyman Installer, Senior Installer, Master Installer)

Products Required:
( TFL Material, Accessories, Special Order)

Back to top


Anchor
Tools-&-Hardware
Tools-&-Hardware
Tools Required

Image Removed

Tool #1

Image RemovedTool #2Image Added

Drill Driver/Impact Drill

Image Added

4' Level

Tool #3

Tool #4

Tool #5

Tool #6

Tool #7

Tool #8

Tool #9Step Ladder

Image Added

Hammer

Image Added

Par Feet (Option 1)

Image Added

Shims (Option 2)

Hardware Required

Image Removed

Hardware #1

Image Removed

Hardware #2

Image Removed

Hardware #3

Hardware #4

Hardware #5

Hardware #6

Image Added

3/4” x #8 Screws

Back to top


Anchor
Installation-Steps
Installation-Steps
TitleInstallation Steps

Panel
panelIconId1f9ba
panelIcon:safety_vest:
panelIconText🦺
bgColor#FFFAE6

Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

Installation Steps Go Here

.

  1. Remove baseboards (if applicable) for all areas located behind a system.

    1. Prior to removal, cut caulk line.

    2. Using a hammer and pry bar, start prying baseboard away from the wall.  Pry at stud locations to minimize drywall damage.

    3. Try to start removal in an area that will be concealed if any wall damage is done.

Image Added

If baseboards are not being removed, notch partitions based on baseboard size and elevation measurements.

  1. Ensure you have checked for the high point in the space.

  2. Hang system rail according to floor-based process steps.

  3. Prepare and hang partitions. If using par feet for support, attach par feet during this step.

  4. Install top, middle and bottom fixed shelves.

  5. Levelsystem from the high spot in the room. Slide your level across the top of the system and adjust the partition suspense brackets accordingly.

    1. Lower the partition to the ground at the high spot and level the remainder of the system.

  6. Plumbthe system from left to right using a 4-foot to ensure it is square.

If partitions are longer than 6 feet, check for levelness in two spots: high and low.

  1. If using shims for support, place them under the front and back of each partition.

    1. Ensure they are flush or inset half of the partition width if visible.

Image Added

Back to top


Anchor
Related-Training-Materials
Related-Training-Materials
Related Training Materials

Link #1
Link #2Skeleton Fundamentals
PPE Matrix

Back to top


Anchor
Final-Steps-&-Delivery
Final-Steps-&-Delivery
Final Steps & DeliveryNext Steps:

Complete the Installation
Touch-Up and Quality Check System
Clean System
Deliver to Customer

Back to top


Anchor
Certification-Steps
Certification-Steps

Panel
panelIconId270d
panelIcon:writing_hand:
panelIconText✍️
bgColor#E3FCEF

Certification Steps:

Back to top


Anchor
Terms-&-Definitions
Terms-&-Definitions
Terms & Definitions

Elevation

The CAD Design Plan created by the Design Consultant with the client.

Level

The wall or system is horizontally straight.

Plumb

The wall or system is vertically straight.