This page explains the process for installing stacked systems. The steps below outline the order of completing the multiple levels and is not a comprehensive list of process steps. Ensure to follow the included links to the applicable pages for full process instructions.
Page Contents
...
...
Process Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
...
Anchor | ||||
---|---|---|---|---|
|
...
Installer Level Required:
...
Apprentice
...
Installer
...
Products Required: TFL Material, Accessories, Special Order
...
Anchor |
---|
...
Tool #1
Tool #2
Tool #3
Tool #4
Tool #5
Tool #6
Tool #7
Tool #8
Tool #9
Hardware Required
Hardware #1
Hardware #2
Hardware #3
Hardware #4
Hardware #5
Hardware #6
|
...
Process Steps
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance |
...
. |
Prepare for the installation
Hang all pieces of rail for the lower sections and install all components.
Expand | ||
---|---|---|
| ||
|
Hang all pieces of rail for the upper sections and install all components.
Expand | ||
---|---|---|
| ||
|
...
Anchor | ||||
---|---|---|---|---|
|
Skeleton Fundamentals
Floor-Based Systems
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
...
Anchor | ||||
---|---|---|---|---|
|
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.
...
Anchor | ||||
---|---|---|---|---|
|
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Certification Steps:
|
...
Anchor | ||||
---|---|---|---|---|
|
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
|
Click here to submit your own tip from the field
...
...
BOM
...
Bill of Materials; parts list
...