The purpose of this page is to outline the process of installing a MyCube safe. Prior to completing this process, ensure you have completed the installation of the component the safe will be in.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes


Anchor
Skill-Requirements
Skill-Requirements
Types of Installation: Floor-Based

Installer Level Required: Journeyman Installer

Products Required: Special Order

Back to top


Anchor
Tools-&-Hardware
Tools-&-Hardware
Tools Required

image-20240702-124256.png

Tape Measure

image-20240702-124339.png

Drill Driver/Impact Drill

image-20240702-124352.png

1/2” Drill Bit

image-20240702-124407.png

Stud Finder

image-20240702-124352.png

3/16” Drill Bit

Back to top


Anchor
Installation-Steps
Installation-Steps
Installation Steps

Panel
panelIconId1f9ba
panelIcon:safety_vest:
panelIconText🦺
bgColor#FFFAE6

Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. Confirm the location of the safe on the elevation.

Expand
titleClick for more information
  • The elevationwill contain an image of a safe.

  • Ensure there is no obstruction in the way of the safe’s location.

    • If there is, contact your manager or the design consultant before moving forward.

image-20240619-211637.png

  1. Unpack the safe from the box and remove all contents.

  2. If Applicable: Confirm if there is a wall outlet in the vicinity of the safe’s location.

Expand
titleClick for more information
  1. Place the safe on the shelf or in the drawer.

Expand
  • If Applicable: Plug in the power cord as you position the safe.

  • Center the safe on the shelf unless otherwise indicated on the elevation.

  1. Drill for securement of the safe to the bottom and back of the component.

Expand
titleClick for more information
  • If the safe is being attached directly to the wall, locate any studs behind the safe.

  • Make a mark through all securement holes on the safe.

  • Remove the safe and drill for all securement points

    • If the safe is being attached directly to the wall, secure to studs, or drill for and insert toggles.

    • Drill through the remaining securement points using a 3/16” drill bit.

The Mycube Fire Safe is only secured to the bottom through one securement point. Be sure to lift the carpet and remove the fire cover cap to drill. Replace after secured.

  1. Secure the safe.

Expand
titleClick for more information
  • Place the safe back in position and secure using the provided screws and washers.

  • If the safe is being attached directly to the wall with toggles, secure with toggle bolts through the applicable holes.

  1. Complete the setup of the safe.

Expand
titleClick for more information
  • Place the carpet along the bottom of the safe’s interior.

  • If applicable: Place the shelf inside the safe.

  • If applicable: Insert provided batteries into the keypad.

  1. Complete the remainder of the installation.

  2. Complete the final walkthrough with the customer and demonstrate the safe.

Expand
titleClick for more information
  • Provide the customer with keys and informational paperwork.

  • Explain that any technical issues are best directed through MyCube and their customer service.

  • Optional: If the customer requests assistance with setting the code, walk them through the process. Turn away when the customer inputs their code.

Back to top


Anchor
Related-Training-Materials
Related-Training-Materials
Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Video: Shelf Safe Installation
Video: Fire Safe Installation
Video: Drawer Safe Installation
Product Feedback Form

Back to top


Anchor
Final-Steps-&-Delivery
Final-Steps-&-Delivery
Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.

Back to top


Anchor
Certification-Steps
Certification-Steps

Panel
panelIconId270d
panelIcon:writing_hand:
panelIconText✍️
bgColor#E3FCEF

Certification Steps:

  1. The safe is in the correct location according to the elevation.

  2. The safe is secured to the wall (if applicable) and shelf below.

  3. The safe has been demonstrated during the final walkthrough with the customer.

Back to top


Anchor
Tips
Tips
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Panel
panelIconId1f5e3
panelIcon:speaking_head:
panelIconText🗣️
bgColor#DEEBFF

Click here to submit your own tip from the field.

Back to top


Anchor
Terms
Terms
Terms & Definitions

BOM

Bill of Materials; parts list

Elevation

The CAD Design Plan created by the Design Consultant
with the client.

Back to top


Anchor
BOM
BOM
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.

SAF

Safe

SFI

MyCube Safe Insert

The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.