This page explains the process for installing stacked systems. The steps below outline the order of completing the multiple levels and is not a comprehensive list of process steps. Ensure to follow the included links to the applicable pages for full process instructions.

Page Contents

...

Skill Requirements

...

Process Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field

...

Anchor
Skill-Requirements
Skill-Requirements
Types of Installation: Off-the-Floor, Floor-Based

...

Installer Level Required:

...

Apprentice Installer

...

Products Required: TFL Material, Accessories, Special Order

Back to top

...

Anchor

...

Tool #4

Tool #5

Tool #6

Tool #7

Tool #8

Tool #9

Hardware Required

Image Removed

Hardware #1

Image Removed

Hardware #2

Image Removed

Hardware #3

Hardware #4

Hardware #5

Hardware #6

Back to top

...

...

Image Removed

Tool #2

Image Removed

Tool #3

Installation-Steps
Installation-Steps

...

Process Steps

Panel
panelIconId1f9ba
panelIcon:safety_vest:
panelIconText🦺
bgColor#FFFAE6

Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance

...

.

  1. Prepare for the installation

  2. Hang all pieces of rail for the lower sections and install all components.

Expand
titleClick for more information
  • Install the floor-based systems first. Ensure the entire lower system is installed, level, and plumb.

  1. Hang all pieces of rail for the upper sections and install all components.

Expand
titleClick for more information
  • Follow the floor-based system standards when installing the upper sections.

  • If Applicable: Secure the top cap or countertop between the systems.

  • If Applicable: Use a dowel or biscuit to connect the upper and lower sections together.

  1. Complete the installation.

Back to top

...

Anchor
Related-Training-Materials
Related-Training-Materials
Related Training Materials

Skeleton Fundamentals
Floor-Based Systems
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Product Feedback Form

Back to top

...

Anchor
Final-Steps-&-Delivery
Final-Steps-&-Delivery
Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.

Back to top

...

Anchor
Certification-Steps
Certification-Steps

Panel
panelIconId270d
panelIcon:writing_hand:
panelIconText✍️
bgColor#E3FCEF

Certification Steps:

  1. All lower systems are installed first following floor-based standards.

  2. All upper systems are installed following floor-based standards.

  3. Lower and upper systems are connected to each other.

Back to top

...

Anchor
Tips
Tips
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Panel
panelIconId1f5e3
panelIcon:speaking_head:
panelIconText🗣️
bgColor#DEEBFF
  • Scaffolding may be required for access to upper sections depending on the height of the system.

Click here to submit your own tip from the field

...

Back to top

...

BOM

...

Bill of Materials; parts list

Back to top

...

.

Back to top