This page explains the steps to take for installing accessory racks. This includes belt, tie, scarf, and garment racks. Prior to beginning the installation, ensure you have completed all steps of installing the system skeleton.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes


Types of Installation: Off-the-Floor, Floor-Based

Installer Level Required: Jr. Apprentice Installer

Products Required: Accessories, Special Order

Back to top


Tools Required

Drill Driver/Impact Drill

3/16” Spade Bit

Hardware Required

Scarf Rack

Belt Rack

Tie Rack

Valet Rod

Back to top


Installation Steps

Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. Locate where the accessory is to be installed.

 Click for visuals and more information
  • An accessory is typically indicated with a letter on the elevation.

  • If there are any concerns, consult with the design consultant or your manager.

  • Assess if there are system holes at the installation location. If there are not, check if there are system holes on the other side of the par you can drill there.

    • If there are no holes on either side of the par, you will need to pre-drill before installation of the accessory.

  • Ensure the accessory you have is for the correct side of the component (left/right).

20240507_160258.jpg

  1. If Applicable: Mark and drill holes.

 Click for more information
  • Make marks for where screws will be placed according the location of the accessory. The location is determined by the location indicated on the elevation, or by the customer’s preference.

  • Drill any necessary holes needed to mount the accessory using a 3/16” bit.

  1. Organize the accessory.

 Click for visuals and more information
  • Separate the accessory into the 2 separate pieces: the track and the accessory itself.

Accessory_Separating Rack.gifValet Rod_Separation.gif
  1. Mount the track.

 Click for visuals and more information
  • Mount the track with the open end facing the front of the component.

  • For valet rods: Mount the track with the capped end facing the front of the component.

  • 2 euro screws are needed and are to be inserted in the system holes or pre-drilled holes.

20240507_161115.jpg20240507_160614.jpg
  1.  Attach the accessory and cap the ends.

 Click for more information and visuals
  • Slide the accessory into the track and slide it all the way in.

  • Pull it all the way out to test functionality.

  • For all accessories other than a valet rod: Snap the provided black cap into the front end of the accessory to give it a clean finish.  This also provides a stopping point for when it is pushed back in.

Accessory_Attaching accessory.gifValet Rod_Attachment.gif

Back to top


Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix

Back to top


Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.

Back to top


Certification Steps:

  1. Accessory has been installed in the correct location according to system elevation or customer preference.

  2. The end cap has been installed on the front of the accessory.

  3. The accessory pulls out and pushes in with ease.

Back to top


Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Click here to submit your own tip from the field.

Back to top


Terms & Definitions

BOM

Bill of Materials; Parts List

Component

Individual section of a system formed by a partition on either side.

Elevation

The CAD Design Plan created by the Design Consultant with the client.

Back to top


BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.

BR

Belt Rack

GR

Garment Rod

ST

Scarf Rack

TR

Tie Rack

The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.

Back to top

  • No labels

0 Comments

You are not logged in. Any changes you make will be marked as anonymous. You may want to Log In if you already have an account.