This page explains the steps to take for installing front-mount fascia. Prior to beginning the installation, ensure you completed all steps of installing the system skeleton.
Page Contents
Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes
Anchor | ||||
---|---|---|---|---|
|
Installer Level Required: Apprentice Installer
Products Required: TFL Material
Anchor | ||||
---|---|---|---|---|
|
Tape Measure
Pencil
Miter Saw with Stand
18-Gauge Finish Nail Gun
23-Gauge Pin Nailer
Seam Glue
Wax Crayon
Hardware Required
18-Gauge 2” Finish Nails
23-Gauge 1” Pin Nails
18-Gauge 1 1/4” Finish Nails
Anchor | ||||
---|---|---|---|---|
|
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance. |
Confirm measurements of fascia pieces as indicated by the elevation, as well as the measurement of the nailer needed.
Expand | ||
---|---|---|
| ||
|
Cut nailer and fascia pieces to length using a miter saw.
Expand | ||
---|---|---|
| ||
|
Install nailer piece(s).
Expand | ||
---|---|---|
| ||
Dry fit all cut fascia pieces.
Expand | ||
---|---|---|
| ||
|
Ensure seams are lined up perfectly and glue all seams using miter bond.
Expand | ||
---|---|---|
| ||
Install all fascia pieces.
Expand | ||
---|---|---|
| ||
|
Using the corresponding color wax crayon to the system’s finish, crayon all nail holes and touch up the seams.
Inspect the fascia for imperfections from the installation process.
Anchor | ||||
---|---|---|---|---|
|
Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Anchor | ||||
---|---|---|---|---|
|
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.
Anchor | ||||
---|---|---|---|---|
|
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Certification Steps:
|
Anchor | ||||
---|---|---|---|---|
|
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Click here to submit your own tip from the field.
Anchor | ||||
---|---|---|---|---|
|
BOM | Bill of Materials; Parts List |
Elevation | The CAD Design Plan created by the Design Consultant with the client. |
Nailer | A piece of support trim/molding nailed on to create additional stability for trim pieces. |
Anchor | ||||
---|---|---|---|---|
|
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.
FAB | Fascia Base |
FAF | Fascia Front |
NLR | Nailer |
Text Note | Scribe to the wall |
The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.