The purpose of this page is to outline the process for installing blind corner doors. Prior to beginning this process, ensure the full system skeleton has been completed.
Page Contents
Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes
Anchor | ||||
---|---|---|---|---|
|
Installer Level Required: Journeyman Installer
Products Required: TFL Material, Special Order
Anchor | ||||
---|---|---|---|---|
|
Drill Driver/Impact Drill
Screw Driver
Blue Tape
Hardware Required
Blind Corner Hinge
Hinge Mounting Plate
Anchor | ||||
---|---|---|---|---|
|
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance. |
Install the hinge plates on the manual panel.
Expand | ||
---|---|---|
| ||
|
Place the manual panel against the corner par. The panel should be 1-3” longer than the depth of the partition.
Attach the panel.
Attach the blind corner hinges to the door.
Lift the door into place and snap it into the hinge plates.
Expand | ||
---|---|---|
| ||
|
Open and close the door 1-2 times to test functionality and clearance of the corner.
Adjust the hinges so the door is in-line with the cabinet.
Expand | ||
---|---|---|
| ||
|
Install handle or knob. Refer to the decorative hardware guide for hardware specifications.
Expand | ||
---|---|---|
| ||
|
Anchor | ||||
---|---|---|---|---|
|
Skeleton Fundamentals
Complete the Installation
System Touch Ups
Delivery to the Customer
PPE Matrix
Anchor | ||||
---|---|---|---|---|
|
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.
Anchor | ||||
---|---|---|---|---|
|
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
Certification Steps:
|
Anchor | ||||
---|---|---|---|---|
|
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Panel | ||||||||
---|---|---|---|---|---|---|---|---|
| ||||||||
|
Click here to submit your own tip from the field.
Anchor | ||||
---|---|---|---|---|
|
BOM | Bill of Materials; parts list |
Elevation | The CAD Design Plan created by the Design Consultant with the client |
Anchor | ||||
---|---|---|---|---|
|
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.
HDR | Hinged Door |
HIN | Hinge |
HL | Handle |
INS | Insert |
MP | Manual Panel |
PRO | Profile |
The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.