This page explains the steps to take for installing vertical uprights. Prior to beginning the installation, ensure you completed all steps of installing the system skeleton.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
BOM Codes


Anchor
Skill-Requirements
Skill-Requirements
Types of Installation: Off-the-Floor, Floor-Based, Virtuoso, Wall Bed

Installer Level Required: Apprentice Installer

Products Required: TFL Material

Back to top


Anchor
Tools-&-Hardware
Tools-&-Hardware
Tools Required

Tape Measure

image-20240422-135424.png

Angle Ratchet Pozi #2

image-20240422-135532.png

Pozi #2 Screwdriver

image-20240422-151410.pngImage Added

Wood Glue

Hardware Required

image-20240422-140141.png

Dowels
(Hafele 267.83.230)

Back to top


Anchor
Installation-Steps
Installation-Steps
Installation Steps

Panel
panelIconId1f9ba
panelIcon:safety_vest:
panelIconText🦺
bgColor#FFFAE6

Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. Locate and inspect all parts.

Expand
titleClick for more information
  • The bottom shelf should be drilled on the top side and the top shelf should be drilled on the bottom side.For the bottom shelf, ensure that the top surface is pre-drilled to accommodate dowels. On the top shelf, make sure it is pre-drilled on the bottom side to align with the dowels on the bottom shelf.

  • The vertical shelf should be drilled on both ends.

  1. Place dowels in both ends of the vertical upright.

Expand
titleClick for more information
  • Place a small dollop of wood glue into the pre-drilled holes on the upright prior to inserting the dowels to secure the dowels in place.

If Applicable: Trim the length of the dowel(s) to ensure a tight fit between the pieces.

  1. Secure the bottom fixed shelf between the partitions, ensuring the pre-drilled holes are facing upwards.

  2. Place the vertical upright dowels into the pre-drilled holes on the bottom fixed shelf.

  3. Install the top fixed shelf.

Expand
titleClick for more information
  • Once all vertical uprights have been inserted, ensure the pre-drilled holes on the top fixed shelf are facing downward and align the holes with the dowels and the cams with the Rafix pins.

  • Carefully tap down on the top shelf to secure in place.

Back to top


Anchor
Related-Training-Materials
Related-Training-Materials
Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix

Back to top


Anchor
Final-Steps-&-Delivery
Final-Steps-&-Delivery
Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.

Back to top


Anchor
Certification-Steps
Certification-Steps

Panel
panelIconId270d
panelIcon:writing_hand:
panelIconText✍️
bgColor#E3FCEF

Certification Steps:

  1. Top and bottom shelves are locked in.

  2. Dowels have been used to connect the vertical pieces to the horizontal fixed shelves.

  3. There are no gaps between the vertical pieces and the horizontal fixed shelves.

Back to top


Anchor
Tips
Tips
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Panel
panelIconId1f5e3
panelIcon:speaking_head:
panelIconText🗣️
bgColor#DEEBFF

Click here to submit your own tip from the field.

Back to top


Anchor
BOM
BOM
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.