Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Version History

Version 1 Next »

This page explains the steps to take for installing a fusion slatwall system. Prior to beginning, ensure you have followed all steps to prepare for the installation.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Terms & Definitions


Types of Installation: Off-the-Floor, Floor-Based, Wall Bed

Installer Level Required: Apprentice Installer

Products Required: TFL Material, Accessories, Special Order

Back to top


Tools Required

image-20240423-133455.png

Tape Measure

image-20240423-133518.png

Drill Driver/Impact Drill

Countersink Bit

2' Level

1/2” Wing Bit

image-20240423-134757.png

Pencil

image-20240423-134843.png

Miter Saw

Hardware Required

image-20240423-133418.png

3/4” Self-Tapping Screw

Toggles & Bolts

Back to top


Installation Steps

Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. Locate all parts based on the elevations and BOM. Ensure you have tracks, boards and trim.

  2. Understand where on the wall the system will go.

 Click for more information
  • Use the elevation indicators and measurements as a guide.

  • Locate studs and make marks for track securement points.

  1. Using the countersink bit, pre-drill holes in the track pieces in alignment with stud locations.

  2. Screw the first piece of the track to the wall and ensure it is level.

 Click for more information
  • Start with the bottom piece.

  • If there are no studs within 3” of the end of the track piece, you will need to use a toggle and bolt at the end of the track.

If the design indicates a piece of ¼” board at the bottom below the bottom track, the “J” channel must be mounted at the bottom below the ¼” board. The bottom track’s groove is to then be placed along the top of the ¼” board. Continue the process from Step 4 onward.

  1. Insert the board material.

 Click for more information
  • Ensure it is fitting firmly in the track.

If you are having a hard time inserting the board, loosen the screws until it fits into the track and retighten the screws.

  1. Repeat step 4 by placing the next track piece on top of the already installed piece. There is a groove in the track for them to fit together.

  2. Repeat Step 5 and continue until all track and board pieces are secure on the wall.

  3. Install trim pieces.

 Click for more information
  • From the bottom to the top, the channel needs to cover the whole side on both sides of the system.

  • Pre-Drill the trim to line up with the center of the rib on the wall track.

  • Do not drill any screws in the end of the ribs.

  • Secure using ¾” self-tapping.

  • There should be at least 1 screw in each wall track.

If the trim pieces are not cut for you, you will need to cut the “L” channel to the height of the fusion wall using a miter saw.

Back to top


Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix

Back to top


Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.

Back to top


Certification Steps:

  • The track was installed with the grooves for accessories on the bottom.

  • Trim has been installed.

  • Screw caps have been used.

  • If Applicable: accessories have been set on the track and locked into place with accessory cover caps.

Back to top


Terms & Definitions

BOM

Bill of Materials; the parts list

Elevation

The CAD Design Plan created by the Design Consultant with the client.

Back to top

  • No labels