Fixed Shelves

Table of Contents
03. Skeleton Fundamentals

LIVE

This page explains the steps to take for installing a standard TFL fixed shelf. Prior to beginning this process, ensure the rail has been hung and partitions are prepped and hanging on the rail for all spaces.

 

Page Contents


Types of Installation: Off-the-Floor, Floor-Based, Wall Bed

Installer Level Required: Jr. Apprentice Installer

Products Required: TFL Material


Tools Required

Pozi #2 Screwdriver

Angle Ratchet Pozi #2

 

 

Hardware Required

Fixed Shelf Rafix Pins

Rafix Double-Ended Dowel (Optional)

 


Installation Steps

Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

 

  1. Ensure the Rafix pins are in the partitions in the appropriate locations. This should be done while prepping the partition.

If shelves are being installed on either side of a shared partition, double-ended dowels may be used and inserted from left to right.

  1. Locate the shelves in the staging area.

  2. Double check the measurements on the BOM and the label to ensure the correct sizes are being placed in the correct location(s).

  1. Inspect the shelf for chips, damage, and missing or damaged Cams.

  • Inspect the shelf prior to removing the sticker in case the shelf needs to be replaced due to damage.

  1. Check the Cams and ensure they are positioned in the shelf correctly and in the open position.

  • Ensure that each cam is aligned correctly and flush with the shelf surface.

  • Ensure that each inner cam is in the open position.

  • If either pieces are not in the correct position, reposition them using a Pozi #2 screwdriver.

  • If the Cams are not in the open position, the Cam may be damaged when placing the shelf and become unusable.

  1. Set the shelf on the Rafix screws and ensure the Cams are sitting on each screw.

Keep fixed shelves right side up.  As these shelves are load bearing, it is important they are installed with the Cam side facing the bottom of the system.

  1. Tighten each Cam clockwise until they stop turning using a Pozi #2 bit screwdriver.

  • Do not overtighten or use a drill to tighten as this will run the risk of damaging the cam.

  • Ensure the screwdriver is completely inserted in the Cam.

  1. Check the shelf for tightness. Gently push upwards to make sure it is locked in place.

  2. Repeat for all remaining shelves, as indicated by an X on the elevation.


Related Training Materials

Skeleton Fundamentals
PPE Matrix


Next Steps: Level, Plumb, Secure the System

 



Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Click here to submit your own tip from the field.


Terms & Definitions

BOM

Bill of Materials; Parts List

Elevation

The CAD Design Plan created by the Design Consultant with the client.


BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.

SF

Shelf Fixed

TS

Top Shelf

VB

VB; Verbindungen

The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.

Questions? Please e-mail Aleeshya Broome (albroome@calclosets.com)