Sliding Wire Baskets
Table of Contents
Jr. Apprentice to Apprentice Installer
This page explains the steps to take for installing sliding wire baskets. Prior to beginning the installation, ensure you completed all steps of installing the system skeleton.
Page Contents
Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes
Types of Installation: Off-the-Floor, Floor-Based
Installer Level Required: Jr. Apprentice Installer
Products Required: Accessories
Drill Driver/Impact Drill
Hardware Required
Basket with Optional Liner
Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.
Check the included hardware.
Mount the runner to the partition.
Prep the runners and install the basket.
Add basket liner, if indicated on the elevation. Ensure the logo is facing toward the front.
Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Product Feedback Form
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.
Certification Steps:
Runners have been installed in the correct location according to system elevation, and they extend out.
Basket has been placed on the runners correctly.
Basket pulls out and pushes in with ease.
If applicable: Basket liner is installed.
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Click here to submit your own tip from the field.
BOM | Bill of Materials; the parts list |
Elevation | The CAD Design Plan created by the Design Consultant with the client. |
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.
BA | Basket |
BAW | Basket Wrap |
The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.