The purpose of this page is to outline to process of installing or attaching multiple office accessories, including magnetic marker boards and fabric/tack boards. If you are installing a non-magnetic marker board, review the press-in panel instructions.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Marker Boards
Tack Boards
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes


Anchor
Skill-Requirements
Skill-Requirements
Types of Installation: Off-the-Floor, Floor-Based, Wall Bed

Installer Level Required: Journeyman Installer

Products Required: Accessories, Special Order

Back to top


Anchor
Tools-&-Hardware
Tools-&-Hardware
Tools Required

Drill Driver/Impact Drill

Tape Measure

1/2” Drill Bit

image-20240223-144606.png

18-Gauge Nail Gun

image-20240614-143300.png

Liquid Nails

4' Level

image-20240606-144619.png

Stud Finder

Hardware Required

18-Gauge 1 1/4” Nails

Toggle Bolts

2 1/2” Screws

Back to top


Anchor
Installation-Steps
Installation-Steps
Installation Steps

Panel
panelIconId1f9ba
panelIcon:safety_vest:
panelIconText🦺
bgColor#FFFAE6

Personal Protective Equipment (PPE) must beworn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

Marker Boards

Anchor
Marker
Marker

  1. Determine the height of the board based on the elevation. If this is not noted, reach out to the design consultant.

  2. On the board, measure from top of the panel down to the center of the pre-drilled hole in the bottom track. Note this measurement.

  3. Repeat this measurement for bottom bottom track. Note this measurement.

  4. Remove tape to separate the pieces of the Z cleat and remove bottom track

  5. Measure from floor to indicated height of accessory

  6. Transfer both cleat marks to the wall.

  7. Draw a level line for both bottom cleats.

  8. Place the bottom cleat on the wall, with the line centered on the holes.

  9. Determine location of studs for securement points. Drill for any toggles using a 1/2” drill bit.

All holes on the cleat should be used for securement. At least 2 studs should be hit for securement.

  1. Secure using 2.5” screws and toggles through all holes on the bottom cleats.

  2. Hook the board onto the bottom cleats.

Fabric/Tack Boards

Anchor
Tack
Tack

  1. Complete the full installation of the adjacent or surrounding system.

  2. Measure the area to ensure the tack board will fit.

  3. Place circle of liquid nails on the back of the tack board.

  4. Place the tack board on the wall.

  5. Secure in place using 1 1/4” nails. Ensure they sit below the fabric so they are not seen.

Back to top


Anchor
Related-Training-Materials
Related-Training-Materials
Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Product Feedback Form

Back to top


Anchor
Final-Steps-&-Delivery
Final-Steps-&-Delivery
Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and deliveringthe final product.

Back to top


Anchor
Certification-Steps
Certification-Steps

Panel
panelIconId270d
panelIcon:writing_hand:
panelIconText✍️
bgColor#E3FCEF

Certification Steps:

Back to top


Anchor
Tips
Tips
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Panel
panelIconId1f5e3
panelIcon:speaking_head:
panelIconText🗣️
bgColor#DEEBFF

Click here to submit your own tip from the field.

Back to top


Anchor
Terms
Terms
Terms & Definitions

BOM

Bill of Materials; parts list

Back to top


Anchor
BOM
BOM
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.

Text Note

Standardized Magnetic Markerboard

Text Note

Leather Desk Blotter

The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.