This page explains the steps to take for building and installing an island. Prior to beginning the installation, ensure you completed all steps of preparing for the installation.

Page Contents

Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes


Types of Installation: Off-the-Floor, Floor-Based, Virtuoso, Wall Bed

Installer Level Required: Apprentice Installer

Products Required: TFL Material, Accessories, Special Order

Back to top


Tools Required

image-20240322-133243.png

Tape Measure

image-20240322-133253.png

Pencil

image-20240322-133308.png

Drill Driver/Impact Drill

image-20240322-133322.png

#2 Pozi Screwdriver

image-20240322-134221.png

4' Level

image-20240613-133607.png

18-Gauge Nail Gun

Hardware Required

image-20240322-133435.png

#8 x 1 1/4” Screw

image-20240322-133435.png

#8 x 3/4” Screws

image-20240322-133450.png

Par Feet

image-20240322-133509.png

Shims

image-20240613-133645.png

18-Gauge 1 1/4” Nails

Back to top


Installation Steps

Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. Measure the placement of the island to ensure proper space to move around. Determine the spacing from the elevation.

If the spacing is not indicated, consult with the designer or the customer.

  1. Prep all partitions for the island.

 Click for visuals
image-20240322-133726.png
  1. Place fixed shelves between the partitions as specified by the elevation.

 Click for visuals
image-20240322-133801.png
  1. Place the assembled island component shelf-side down; this will give you more of a sturdy platform to install your backing and make it easier to square the unit.

 Click for visuals
image-20240322-133853.png
  1. Place backing within the assembled component; the backing should be resting on the shelves installed in step 7.2.3.

  2. Ensure the backing is flush in all four corners of the assembled component.

 Click for visuals
image-20240322-133934.png
  1. Attach backing to each section, ensuring the backing is not sitting proud of the partitions.

 Click for visuals and more information
  • Make a pencil mark on the backing to indicate where the fixed shelves are for alignment.

  • Attach the backing to the fixed shelves using 18-gauge 1 1/4” nails. Use 2 per shelf.

Be aware of screws can be placed to be hidden.  If screws cannot be hidden, use fast caps.

  1. If the island is a multi-component island, install fixed shelves on the remaining side of the island.

  2. Ensure the placement is accurate according to the elevation, and the island is level.

 Click for visuals and more information
  • Level one side of the island, place a level across all partitions on the island, and level using par feet or shims.

image-20240322-134144.png

If installing base moulding on the island, always use a miter joint for seams.

  1. Install the countertop.

 Click for visuals and more information
  • Check to ensure all overhangs are even or installed according to the elevation.

image-20240322-134429.png

Back to top


Related Training Materials

Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix

Back to top


Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.

Back to top


Certification Steps:

  1. Island is in the correct location according to the elevation.

  2. Island is level.

  3. Backing is nailed for attachment to fixed shelves.

  4. All accessories, drawers, additions are installed on the island according to the elevation.

Back to top


Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Click here to submit your own tip from the field.

Back to top


Terms & Definitions

BOM

Bill of Materials; Parts List

Elevation

The CAD Design Plan created by the Design Consultant with the client.

Back to top


BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.