This page explains the steps to take for installing press-in backing. This page also contains the information for prepping partitions using the traser suspension bracket. This process refers to several elements of installing the system skeleton.
Page Contents
Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes
Types of Installation: Off-the-Floor, Floor-Based, Wall Bed
Installer Level Required: Apprentice Installer
Products Required: TFL Material, Accessories, Special Order
Suction Cup
Drill Driver/Impact Drill
Pozi #2 Bit
Hardware Required
Traser Suspension Brackets
Rafix Screw
L Brackets
Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.
Prepare the partitions using the Traser suspension brackets and all applicable hardware
Hang the partitions on the system rail.
Level, plumb, and secure the system using the two-way adjustments on the Traser brackets. Secure using small metal L brackets.
If system contains lighting: Run any wiring or light leads behind the system.
Before installing any Press-in Backing panel, all fixed shelves must be installed, electrical wiring must be run behind the system, and the system must be leveled and secured to the wall.
Position backing in place, aligning cams with the rafix pins in the back of the partitions.
Firmly press the backing into place and ensure it is secured to the pins.
Complete the installation with any remaining system elements and accessories.
To Remove Press-In Backing
Removing short panels: Place one suction cup at the center of the panel, centered on the height, and pull firmly to remove in a single motion.
Removing tall panels: Place one suction cup towards the top of the panel and one towards the bottom of the panel, centered on the
Do not attempt to move the panel side-to-side or force out; this may cause damage to the material.
Skeleton Fundamentals
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Product Feedback Form
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.
Certification Steps:
Partitions were prepped using Traser suspension brackets.
All steps were completed to install the system skeleton elements needed prior to press-in backing.
If applicable: All lighting wiring was placed behind panels.
Backing panels are installed in the correct location and cams are set on rafix pins.
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Click here to submit your own tip from the field.
BOM | Bill of Materials; Parts List |
Level | The wall or system is horizontally straight. |
Plumb | The wall or system is vertically straight. |
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.
PIB | Press-In Backing Panel |
The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.