The purpose of this page is to outline the process for installing fixed shelves and vertical dividers using The Leaman™ Connector. Prior to beginning this process, ensure the system rail is hung, and partitions are hung, level, plumb, and secured. This process does not apply to Connecting Shelves using The Leaman™.

 

Page Contents


Types of Installation: Off-the-Floor, Floor-Based

Installer Level Required: Apprentice Installer

Products Required: TFL Material, Special Order


Tools Required

 

image-20240904-200703.png

Soft Faced Mallet

image-20240904-200722.png

Drill Driver/Impact Drill

Phillips Bit

4mm Hex Key

The Leaman™ Dowel Drilling Jig

The Leaman™ Dowel Insertion Jig

 

Hardware Required

The Leaman™ Dowel

The Leaman™ Insert

8mm Euro Screw
19mm back-to-back applications

11mm Euro Screw
Thicker material applications

 

 


Installation Steps

Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.

  1. If Applicable: Assemble the Leaman™ Insert into the partitions.

  • Use a soft faced mallet, pound the insert into the partition until it is flush, or slightly sub-flush, with the face of the partition.

  • For 19mm back-to-back applications: Secure each insert using an 8mm Euro Screw on a low torque setting until the screw is fully seated in the countersink.

    • For all other applications, an 11mm Euro Screw can be used.

  1. If Applicable: Insert the Leaman™ Dowel into the supported part.

  • Identify the access hole side of the supported part

  • Ensure the flat side of the dowel faces the access hole side

  • Insert the dowels into the edge hole as far as possible, and use the Leaman™ Dowel Insertion Jig into the supported part until the insertion tool bottoms out on the shelf

  • Flip the supported part and repeat the process on the other side

Partitions may be sent with the inserts already in place, and may only need the euro screw to be secured to each insert. Shelves may be sent to the field with the dowels already in place.

  1. Install The Leaman™ shelf by connecting the dowels into the partition inserts.

  • Tilt the Supported Part into the component so that it does not catch or scratch the material.

  • Starting with one side, align the Dowel Plungers with the front of the keyhole on the Leaman Insert 

  • Push the shelf towards the back of the component until dowels on both sides slide to the back of the keyed slot of the insert.

  • Check that all 4 dowels are properly seated in the back of the keyed slot by shaking each corner of the shelf. The part should not be able to move more than 1/8”

  • Before locking the part, adjust it to be flush with the partitions.

    • There is some front-to-back tolerance that you can flush the part with the partition as needed.

The location of the access hole will be indicated on the elevation using the following symbols:

v = Bottom of shelf

^ = Top of shelf

< = Left of Vertical Divider

> = Right of Vertical Divider

  1. Lock the cam in the dowel using a 4mm hex key and rotate it 1/4 turn (90 degrees).

 

  1. If Applicable: Install standard backing or press-in backing panels.

  2. Complete the remainder of the installation.

 

 

Removing a Leaman Shelf

  1. Unlock all Leaman™ Dowels by putting a 4mm Hex Key in the access hole and rotating ¼ turn counterclockwise 

  2. Pull the Part straight out until the Dowel plungers are no longer seated in the Inserts 

  3. Tilt the Part and pull out the rest of the way 

 

 

Manually Drilling for a Leaman Dowel

  1. The Leaman Dowel Drilling Jig can be used to assist with manually drilling a shelf for the Dowel. 

  2. Ensure the jig is set to the correct board thickness for the application 

  1. Using a 12mm drill bit, drill the edge hole at least 45mm deep. 

  1. Next, use the jig to drill the ¼” access hole 

 


Related Training Materials

Skeleton Fundamentals
Complete the Installation
The Leaman™ Connecting Shelf
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix


Final Steps & Delivery

  1. Inspect the installation and complete any touch ups if necessary.

  2. If there are no more components to install, remove all stickers/labels.

  3. If there are no more components to install, complete the clean up process.

  4. If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.



Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.

Click here to submit your own tip from the field.


Terms & Definitions

BOM

Bill of Materials; parts list

Elevation

The CAD Design Plan created by the Design Consultant with the client

Supported Part

TFL material utilizing The Leaman™ Connector

The Leaman™

The Leaman is named in honor of Edward Leaman, our former Chief Brand & Design Officer. A leader and visionary, Edward helped evolve the California Closets brand by consciously “connecting” the work we do to who we are. He was humble, steadfast, and critical to defining our difference, which is exactly how The Leaman will distinguish the concealed visual appeal and experience of our Suite Hardware. 


BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.

 

 

 

 

The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.

Questions? Please e-mail Aleeshya Broome (albroome@calclosets.com)