This page explains the steps to take for installing a complex setup of LOOX5 lighting. This includes multiple drivers, distribution boxes, groups, and switches. Prior to beginning the installation, ensure you have completed all steps of installing the system skeleton. All top and bottom fixed shelves should be installed. There should be no backing pieces installed in the system at this time.
Page Contents
Skill Requirements
Tools & Hardware
Installation Steps
Related Training Materials
Final Steps & Delivery
Certification
Tips from the Field
Terms & Definitions
BOM Codes
Types of Installation: Off-the-Floor, Floor-Based, Virtuoso, Wall Bed, Paxton
Installer Level Required: Apprentice Installer
Products Required: TFL Material, Accessories, Special Order
Jigsaw
3/8” Drill Bit
Drill Driver/Impact Drill
Pencil
Angle Ratchet Pozi #2
Screwdriver Pozi #2
Tape Measure
Multi-Tool
Blue Tape
Personal Protective Equipment (PPE) must be worn at all times when handling material and operating the power tools mentioned throughout this process. Review the PPE Matrix for further guidance.
Test the light functionality.
Plan your lighting setup.
If Backing is not split: Create access holes for backing pieces.
If Backing is split: Install each lit fixed shelf and allow leads to fall or pull them to their respective distribution box location.
Plug the leads into the ports of the distribution box.
If a Connect Mesh Network is to be setup: Follow the Connect Mesh User Guide.
If a wired switch is to be connected: Attach the switch lead to the distribution box and ensure the switch is functioning according to its abilities.
If one receiver is controlled by multiple switches, a multi-switch box is needed to connect the switches.
Attach the switch to the system in accordance with the system’s elevation.
If the customer has opted to control the lighting by their existing wall switch, test the switch to ensure it is controlling the driver's power.
Install all backing panels, and complete the remainder of the installation in accordance with the system’s elevation.
Connect Mesh User Guide
Skeleton Fundamentals
360Share Lighting Channel
Complete the Installation
System Touch Ups
Cleaning the System & Jobsite
Delivery to the Customer
PPE Matrix
Product Feedback Form
Inspect the installation and complete any touch ups if necessary.
If there are no more components to install, remove all stickers/labels.
If there are no more components to install, complete the clean up process.
If there are no more components to install, complete the Professional Installation Experience by walking through the space with the customer and delivering the final product.
Tips from the Field
Tips submitted by fellow installers and leaders in the field. These optional tips are intended to make this install process simpler.
Click here to submit your own tip from the field.
BOM | Bill of Materials; Parts List |
Distribution Box | Box that plugs into the Driver which light leads and |
Driver | Source of power for the distribution boxes and lights. |
Elevation | The CAD Design Plan created by the Design Consultant |
Lead | The cord connecting the light to the distribution box. |
BOM Codes
The purpose of this section is to provide guidance when confirming details on the BOM. This list includes all individual parts typically associated with this process.
DRI | Light Driver |
LBB | Wireless Lighting Bus Bar |
LI | Light |
LIR | Light Remote |
LMB | Mesh Box |
LP | Light Additional Parts |
PK | Puck Light |
PSW | Program Light Switch |
RB | Ribbon Light |
Text Note | Lighting Parts |
The codes in the table above are directly from the Corporate CAD database and may not reflect all codes included in the Supported Franchise Database or Independent Franchise Databases.